Anarchy Bridge Closure Update

From North Earlsdon Neighbourhood Association:NENA logo

Thanks to Councillor Taylor who has been able to obtain more detail about the planned bridge closure –

“I have made some enquiries and can confirm that the Council’s Structures team are resurfacing the section of bridge maintained by CCC over 2-3 consecutive night time closures later this month. The TTRO, published last week, states that the order is valid for 6 months but does not actually give the duration or start date (still to be confirmed). I think people may be confusing the validity of the order with the duration of the works. Please see attached.

Once our structures team has a confirmed date for the works, advance information signs will be erected either end of the bridge at least 7 days in advance, the diversion route will be signed via Warwick Road.

Kind regards
Rhian

Rhian Jones
Programme Manager
Coventry City Council”